London olympic swimming pool7/29/2023 ![]() ![]() ![]() The ODA also said that Team Stadium would build the £496m Olympic Stadium. Overall construction costs remained within budget, it added. The Olympic Delivery Authority (ODA) said construction inflation and VAT had raised the price. The east London centre will cost £242m, not the £75m quoted in London's winning bid, despite a reduction in its size. The London 2012 Olympics aquatics centre will cost more than three times as much as originally estimated, it has been confirmed. The centre will host swimming, diving and water polo events ![]()